Owner with the ability to schedule and coordinate the work describes which delivery method?

Prepare for the Design-Build Institute of America (DBIA) Exam 1 with our comprehensive study resources. Explore flashcards and multiple choice questions with detailed explanations to ensure success.

Multiple Choice

Owner with the ability to schedule and coordinate the work describes which delivery method?

Explanation:
When the owner is responsible for scheduling and coordinating the work, this aligns with multiple prime contracting. In this approach the owner signs separate contracts with several prime contractors (for different trades or portions of the project) and takes on the role of integrating those distinct scopes. Because each prime handles its own portion, the owner (often with a construction manager) must manage sequencing, interfaces, and overall schedule to ensure the project comes together. Other methods place the integration and coordination more within a single contractor or emphasize a highly collaborative team approach, rather than the owner actively coordinating multiple separate prime trades.

When the owner is responsible for scheduling and coordinating the work, this aligns with multiple prime contracting. In this approach the owner signs separate contracts with several prime contractors (for different trades or portions of the project) and takes on the role of integrating those distinct scopes. Because each prime handles its own portion, the owner (often with a construction manager) must manage sequencing, interfaces, and overall schedule to ensure the project comes together. Other methods place the integration and coordination more within a single contractor or emphasize a highly collaborative team approach, rather than the owner actively coordinating multiple separate prime trades.

Subscribe

Get the latest from Passetra

You can unsubscribe at any time. Read our privacy policy