In CMAR, construction cost is determined _____ the design is completed.

Prepare for the Design-Build Institute of America (DBIA) Exam 1 with our comprehensive study resources. Explore flashcards and multiple choice questions with detailed explanations to ensure success.

Multiple Choice

In CMAR, construction cost is determined _____ the design is completed.

Explanation:
In CMAR, the construction manager is brought in early during the design process to provide cost estimating, constructability input, and collaboration on budgeting. This early involvement allows a cost baseline to be established while the design is still developing, giving the owner budget certainty and the ability to influence design decisions to control cost. The price is typically refined toward a GMP as design details become clearer, but the key point is that the cost framework is determined before the design is fully completed. Waiting until after design completion would miss the opportunity to steer the project toward cost-effective options that CMAR enables.

In CMAR, the construction manager is brought in early during the design process to provide cost estimating, constructability input, and collaboration on budgeting. This early involvement allows a cost baseline to be established while the design is still developing, giving the owner budget certainty and the ability to influence design decisions to control cost. The price is typically refined toward a GMP as design details become clearer, but the key point is that the cost framework is determined before the design is fully completed. Waiting until after design completion would miss the opportunity to steer the project toward cost-effective options that CMAR enables.

Subscribe

Get the latest from Passetra

You can unsubscribe at any time. Read our privacy policy